Estimation · Quantity takeoff
Concrete slab and pier takeoff from engineering drawings
A concrete-only takeoff for a steel shed: a main slab, a lean-to slab, 13 bored piers, roller door rebates and a slab step, measured from the engineer's slab plan and footing details.
What I did
- Marked up the slab plan to show each slab area, pier type, rebate, step and saw cut, colour-coded by item.
- Worked out pier depths from the footing detail tables and finished floor levels, and calculated concrete volumes for each pier type.
- Built the order quantity: slab plus piers plus rebates, with 5% waste added, rounded to a truck order.
- Counted the mesh sheets, bars and chairs, and measured formwork, step and saw cut lengths.
- Linked every line to the drawing note it comes from and gave it a confidence rating, then listed what the drawings don't show for the site visit.
Outcome
Every quantity in the quote can be checked back to the drawings. Items that need confirming, like the vapour barrier, the pier bar length and pump access, were raised before pricing, not after.